A.-R. Abdul-Aziz
School of Housing Building and Planning, Universiti
Sains
It has been almost twenty years since
privatisation, tolled-highways, end-users, consultation
Influenced by a major shift in economic management
policy in the
Few of the privatised
highway projects have been spared the controversies surrounding toll rates. By
citing several examples, this paper argues that the failure to consult
end-users on charge structure have been strikingly lacking, resulting in
backlash from public opinion. Revision of toll charges, invariably upwards, has
proven to be equally controversial as the public was not made aware of the
impending changes. While Malaysians generally acknowledge the benefits of
tolled highways, the manner in which the market economy is allowed to operate
leaves much to be desired.
This paper begins by citing 5 case studies to highlight the toll
charges controversies. It then discusses the experience of
Figure 1: Location of inter-state privatised highways in Peninsular Malaysia.
Figure 2: Location of privatised
highways in the vicinity of
SPECIFIC ILLUSTRATIONS OF THE
CONTROVERSIES SURROUNDING TOLL CHARGES
The controversies surrounding toll
charges has much to do with
As a consequence of one opposition party gaining tremendous political mileage by bringing disclosing the copious ‘sweeteners’ the government proffered to one particular highway concession company, the Official Secrets Act was amended in 1986 so that the definitions of official secrets also include, among others, government tender documents (even after completion of the tender exercise) and any other documents or materials which ministers and public officials may deem secret or confidential (Jomo, 1995). Henceforth the impact of toll collection on privatised highway users has never been openly debated. Below, the events that have unfolded at five tolled highways are elucidated to illustrate the controversies that have arisen. The information was obtained from publicly available material notably newspapers articles.
Case study 1: North-South Expressway
Under the original concession agreement, PLUS, the concession holder
for the North-South Expressway was entitled to increase the toll incrementally
to cover financing costs and escalating maintenance and service charges; the
first upward change of 33% was supposed to have taken place in 1996, followed
by 6% in 1997 and 1998. The public reacted angrily when it was made known that
PLUS was seeking the government’s consent for the first upward revision. Under
pressure, the government was forced to re-negotiate with PLUS, the outcome of
which was an agreement that toll rise of 20% was scheduled for 1996, 20% for
1997 and 7% for 1998. In return, the government agreed to recompense PLUS RM100
million (equivalent to US$18.9 million using the exchange rate of US$1 is to RM5.30)
for the company’s loss of revenue. When it came for PLUS to increase the toll
in 1998, there were renewed protests from many quarters including the
Federation of Malaysian Consumers Association (FOMCA) and even coalition
parties of the ruling government, as it was felt that such as move was
inappropriate at a time when the country was still in the midst of the Asian
Financial Crisis. Due to overwhelming public resistance, the toll rate increase
was deferred for a year.
In 1999, PLUS and the government entered into a supplemental concession agreement covering amendments pertaining to the toll rate structure, extension of concession period for another 12 years and also share of any excess toll revenue with the government. Arising from that agreement, toll rates for the North-South Expressway were increased that year as part of the toll structure revision. The government paid to PLUS RM87 million for losses arising from the deferment of toll increase in 1998. Under the supplemental agreement, the toll increase of 33.8% every five years as contained in the original agreement was reduced to 26%. Instead of annual increment, increases would be made every five years. In return, the government agreed to compensate PLUS with a loan to offset its projected losses of RM220 million, and extend concession period to 2030 instead of 2016. The five-yearly increment will cease in 2016 after which the rate will remain fixed until the end of the concession period. The government will also have a share in any toll revenue that exceeds projection - the government’s share in excess toll is set at 20 percent for the period 1999-2008, 25 percent for 2009-2020, and 30 percent for 2021-2030.
Set at RM2.60 for cars-users, toll collection for
the
Much to the consternation of the public, the Butterworth-Kulim Expressway, toll was increased by 31.3 percent (from
RM0.80 to RM1.00 at the Kubang Semang
toll plaza and from RM0.80 to RM1.10 at the Lunas
plaza) in 1999, three years after it was opened. The concession holder of the
Butterworth-Kulim Expressway (incidentally together
with the Seremban-Port Dickson Highway) requested for
a ‘safety plan’ from the government as they were facing huge losses due to low
traffic volume, a move that did not go down well with various quarters. A
downward revision of charges for the Butterworth-Kulim
highway was supposed to have been announced concurrently with the one for the
In 1997, when the first section of the
In April 1998, the completed Shah Alam Expressway was officially opened, thus providing and alternative route to the Kuala Lumpur-Klang Federal Highway. This new link is important in that it provides rapid access from Westport, the country’s premier port, to the North-South Expressway as well as the capital. Toll was set at RM1 for car-users. In November 1998, the concession holder announced its intention to increase the toll to RM2.15 from the following year onwards - a proposal that the government later denied is possible without its consent. In early 1999, the government announced that the concessionaire would increase their rates by 20 percent, much to the consternation of parties such as the MTUC and an opposition party, especially when the national economy was still in the throes of the Asian Financial Crisis. Despite the protests, toll charges were allowed to increase effective from March 1st 1999, but only to 20 percent of what was requested, with the government subsidising the rest. That decision apparently pleased all parties concerned as reflected from the disquiet that subsided soon after. In January 2001, the government declined a fresh request for toll increase.
Clearly setting and revising toll charges without prior public
consultation have provoked much resentment in Malaysia. The opposition parties
were quick to capitalise on public opinion by urging
for greater transparency. However from a
narrow set of discontented actors, the sentiment spread to many quarters
including pro-government newspapers and even within the government. Widespread
discontent reached its peak when the Asian Financial Crisis gripped the nation.
The government and highway concession companies were accused of being
insensitive to the plight of the populace and businesses. To restore public
confidence, the Cabinet directed the Ministry of Public Works to study the
possibility of lowering toll rates. The Privatisation
Section of the Economic Planning Unit in the Prime Minister’s Department
engaged an international consulting firm to undertake a nationwide public
survey on six proposed or recently completed privatised
highways. Soon after, a committee comprising of the Prime Minister’s
Department, Finance Ministry and Public Works Ministry was formed to study toll
rise and its implications on four major privatised
highways: the North South Expressway, Shah Alam
Expressway, North-South Expressway Central Link and the KL-Karak
Highway.
As demonstrated from the case studies cited earlier, the quick-fix
solution for the government in addressing the conflict between the private
concession holders and highway users was by compensating the former in return
for not increasing the toll. Such a move however puts tremendous budgetary
pressure, which happens to be the exact opposite of what privatisation
is supposed to do. By early 2001, the government was spending approximately RM1
billion annually to subsidise tolled highway users.
Suspicion soon circulated that the concession companies were being
over-compensated for loss earnings. The computation of loss earnings is
difficult as the information required (e.g. capital costs, operating costs, debt
servicing, projected traffic volume, etc.) is susceptible to wide
interpretations and has therefore worked to the advantage of private highway
operators. Invariably the taxpayers have been the ultimate cost-bearers in all
the re-negotiation process. It has been suggested that public money would have
been better spent on buying up portions or the entire length of these privatised highways.
In fact doubts have even been raised on whether the assistance and
subsidies incorporated in the original concession agreements had benefited
consumers by way of reduced charges or merely improved the financial
performance of the private highway operators. When the public reacted
negatively to the announced toll rates for the newly opened Malaysia-Singapore
Second Crossing, the government investigated on whether the 10,000 hectares of
state land that was given to the concessionaire supposedly to subsidise construction costs was actually passed on to
end-users. As highlighted by Kumaraswamy and Zhang
(2001), there is no evidence that efficiency gains can be made from excessive
subsidies, guarantees and protection.
All this while, the impression of the Malaysian public was that the government has been biased towards profit-seeking concession companies at the expense of public interests. Insulated by the Malaysian government from much of the business and operational risks, highway concessionaires have been largely unscathed, financially or otherwise from the ensuing controversies. Little wonder then that the concessionaires of the Butterworth-Kulim Highway and the Seremban-Port Dickson Highway were bold enough to request for a ‘safety plan’ in light of low traffic volume. Even the public’s anger over toll charges has been largely directed at the government rather than the private companies. A protest poster once labeled the Minister of Public Works ‘the Minister of Tolls’ much to his chagrin. It can be speculated that, realising the Malaysian government’s pro-private sector stance, shrewd promoters of concession highway projects had put forward over-optimistic feasibility studies and financial projections designed to secure the contracts in the safe knowledge that they stand a good chance of making a plea for financial assistance later on. The excuse by the concession company for the Seremban-Port Dickson Highway that low volume was due to the recently completed oil pipeline that dispensed with the need for tankers to distribute petroleum from a nearby oil refinery is difficult to accept as such an infrastructure has a fairly long gestation period and could therefore have been anticipated during the charge fixing stage. It has been documented that the private sector is known to have played ‘perverse games’ (e.g. shifting as much risk as possible to the government and user) that are not necessarily in the interest of consumers (Estache, 2001). Driven by its determination to ensure the success of the privatisation programme, all indications suggest that Malaysia had given in too much to private companies.
To be fair, it has to be mentioned that highways are traditionally
perceived as public goods that require enormous capital and maintenance
investments the private sector is averse to (Winston, 2000). Based on his
experience as a road financing specialist, Purse (2000) points out that it is
very rare for a road to be able to charge sufficiently at toll booths that
would cover both cost and return on equity. Charges set too high would drive
away users who cannot or will not pay. Charges set too low would render the
venture unviable. Hence the provision of grants, guarantees or favourable tax treatment normally extended by host
governments. In addition, he goes on to point out that traffic forecasting is
notoriously difficult; an accuracy factor of plus or minus 10 percent is
considered good. Borrowing large amounts of money on forecasts that are
inherently unreliable is not easy. While these arguments warrant assistance for
highway concessionaires, critics (e.g. Glade, 1989; Nellis
and Kikeri, 1989; Jomo,
1993) still maintain that too much market incentives have been incorporated in
concession agreements in Malaysia.
There are signs however that the government is re-defining its
relationship with concession companies by re-apportioning the risks between the
two sides. For the Damansara-Puchong
Highway project for example, guarantees on traffic volume has been replaced
with soft loans. Furthermore, the government has also restricted toll increases
to only two occasions throughout the 33-year concession period – in 2007 and
2016 – even then only upon request. If the actual income is more than the
projected revenue, the operator is required to reimburse the difference to the
government. The agreement is based on a
new formula that the government hopes to incorporate in future privatised highway schemes. As for other existing
concession holders, the government plans to review the terms of the agreements
so that toll revision is done every three to four years, instead of the present
18 months to 2 years. The government has even mooted the idea that public
holidays or festivities be declared toll-free days for motorists throughout the
nation.
Another reflection of the adjustment process is the government’s recognition of the importance of seeking public opinion as a pre-requisite for the signing of any privatised highway agreement, particularly pertaining to the construction process, length of highway, toll structure and concession period. If truly implemented, this would signify a significant reversal from the government’s policy on non-disclosure. It would also be in line with the advocacy of various writers (e.g. Parker, 1997; Estache, 2001) for transparency in the entire privatisation process. The public has been given the assurance that toll rates for privatised highway projects in future would be kept as low as possible. The Minister of Public Works also promised that a special division within his ministry would be created to receive public complaints about toll charges that can then be forwarded to the Cabinet.
According to the marketing philosophy, the social and economic justification for an organisation’s existence is the satisfaction of the client’s wants (Crompton and Lamb, 1986). In the same vein, it has been suggested that the objective of privatisation should be to bring lasting benefit to consumers (Roseman, 1999). The shift of the Malaysian government towards greater protection of consumer interests would bring the privatisation programme closer in line with what is posited by these writers. As the regulatory body, the Malaysian government must ensure that a balance is struck between the interests of investors, competitors and consumers while at the same time promoting a wider, ‘public interest’ agenda, no matter how complex this may be (Parker, 1997). It must be seen to be fair to all sides and not too lenient to any one party as in the past. The Malaysian government obviously has not performed well in its role as the ‘surrogate consumer’ (Solomon, 1986). Its insensitivity to the sentiments of highway users during the negotiation process bore testimony to this. Even though the opportunity costs of getting it ‘right’ is high in terms of time and management (Vernon-Wortzel and Wortzel, 1989), the current re-positioning exercise is necessary in bringing an end the controversies surrounding privatised highways in Malaysia. It has to be that getting it ‘right’ is a never-ending process, for privatisation is never always smooth and linear (Bienen and Waterbury, 1989). But at least, positive steps are being taken to bring about a better arrangement.
The toll structure controversies in Malaysia raise a fundamental question of how much Malaysians are willing to pay for ease and speed of travel. Is there a toll charge level that is acceptable to all? Or is any charge level too high for them? A study elsewhere has shown that car travelers’ willingness to pay is much lower than once thought and that most travelers do not appear to value travel time savings enough to benefit substantially from optimal tolls (Calfee and Winston, 1998). Besides, it is unlikely that highway users in Malaysia would make a conscious decision to seek cost information about the service they are about to be offered, particularly if the cost of an extended search is high given the difficulty in obtaining such information (Jacoby, Speller and Berning, 1974). When faced with this situation, there is a propensity for consumers to seek information about the service from opinion leaders or through word-of-mouth rather than mass media communications and marketer-dominated sources (Locander and Hermann, 1979; Midgley, 1983). Even if all these suppositions apply to Malaysia, a more open decision-making process would at the very least educate the public on the need to have toll charges set at reasonable levels for concession companies to make viable rates of return on their investments. Consumers need to be made aware that there is a premium to be paid for uncongested service. In other words, the benefits of private infrastructure provision must be ‘sold’ to the public if support for it is to prevail.
Over the last two decades,
Malaysia has managed to rapidly expand its network of highways. The country has
certainly benefited by way of faster movement of goods and people, alleviation
of congestion, increased connectivity across the nation and the emergence of
new growth centers. This would not have been possible if not for the
realignment of the balance between the public and private sector.
Unfortunately, privatised highways in Malaysia have aroused adverse public
opinion that became increasingly untenable over the years. At the heart of the
controversies surrounding privatised highways in
Malaysia is the apportionment of risks between the concession company and the
government that has manifested in among others, toll charge structures
unacceptable to the public. All this while the government has been overly
concerned with private sector participation that too much have been conceded.
Worse, the arrangements struck between the government and private companies
were not revealed to the public. There are indeed signs that the government is
somewhat re-defining its relationship with concession companies to render its
highway privatisation programme more consumer-amenable. The process of finding
the middle ground for all parties concerned is not easy but necessary if toll
charges controversies are to be a thing of the past. Arriving at an acceptable
solution for all is all the more imperative in light of the 19 privatised highways planned under the 2001-2005 five-year
economic plan. The Malaysian experience provides useful lessons that other
countries can benefit from. The power of the consumers in ensuring the
long-term success of privatisation projects is not to
be under-estimated. While for expediency, their interests may be conveniently
ignored during the negotiation process between the government and the private
companies, the repercussion that is latent in nature can detrimentally consume
an even greater amount of time and money to remedy.
Adam, C.,
Cavendish, W. and Mistry, P. S. (1992) Adjusting Privatisation: Case Studies from Developing Countries,
James Currie, London.
Bienen, H. and
Waterbury, J. (1989) The Political Economy of Privatization in Developing
Countries, World Development, 17(5), pp. 617-632.
Calfee, J. E. and
Winston, C. (1998) The Value of Automobile Travel Time: Implications for
Congestion Policy, Journal of Public Economics, 69, pp. 83-102.
Crompton, J. L. and Lamb,
C. H. (1986) Marketing Government and Social Services, John Wiley and
Sons, New York.
Estache, A. (2001) Privatisation and Regulation of Transport Infrastructure in
the 1990s, The World Bank Research Observer, 16(1), pp. 85-107.
Glade, W. (1989) Privatisation in Rent-Seeking Societies, World
Development, 17(5), pp. 673-382.
Jacoby, J.,
Speller, D. E. and Berning, C. K. (1974) Brand Choice
Behaviour as a Function of Information Load:
Replication and Extension, Journal of Consumer Research, 1(June),
pp. 33-42.
Jomo, K.S. (1993) ‘Privatisation in Malaysia’.
In T. Clarke and C. Pitlelis (eds.) The
Political Economy of Privatisation,
Routledge, London, pp. 437-454.
Jomo, K.S. (1995)
‘Overview.’ In K. S. Jomo
(ed.) Privatisation Malaysia: Rents, Rhetorics,
Realities, Westview Press, Boulder, Co., pp.
42-60.
Kumaraswamy, M. M. and
Zhang, X. Q. (2001) Governmental Role in BOT-led Infrastructure Development, International
Journal of Project Management, 19, pp. 195-205.
Lieberman, I. W. (1993) Privatisation: The Theme of the 1990s: An Overview, Columbia
Journal of World Business, 28(2), pp. 8-17.
Locander, W. B. and
Hermann, P. W. (1979) The Effects of Self-Confidence and Anxiety on Information
Seeking in Consumer Risk Reduction, Journal of Marketing Research, 16(May),
pp. 268-274.
Midgley, D. F. (1983)
Patterns of Interpersonal Information Seeking for the Purchase of Symbolic
Product, Journal of Marketing Research, 20(February), pp. 74-83.
Molz, R. (1990) Privatisation in Developing Countries, Columbia Journal
of World Business, 25(1&2), pp. 17-24.
Naidu, G. (1995)
‘Infrastructure.’ In K. S. Jomo (ed.) Privatising Malaysia: Rents, Rhetorics,
Realities, Westview Press, Oxford, pp. 199-218.
Nellis, J. and Kikeri, S. (1989) Public Enterprise Reform: Privatisation and the World Bank, World Development,
17(5), pp. 659-672.
Parker, D. (1997) The
Regulation of Privatised Utilities: Reflections on
the UK Experience, The Review of Policy Issues, 3(3), pp. 3-37.
Purse, N. (2000) Toll Roads-
the Way Ahead, Project Finance, 206, pp. 5-8.
Roseman, E. (1999) Best
Practices for Encouraging Private Sector Investment and Competition in the
Power Industry: Optional or Necessary?, Journal of Project Finance, 5(3),
pp. 15-26.
Solomon, M. R. (1986) The
Missing Link: Surrogate Consumers in the Marketing Chain, Journal of
Marketing, 50(October), pp. 208-218.
Vernon-Wortzel,
H. and Wortzel (1989) Privatisation:
Not the Only Answer, World Development, 17(5), pp. 633-641.
Winston, C. (2000)
Government Failure in Urban Transportation, Fiscal Studies, 21(4),
pp. 403-425.