Timescales

Headington-Hill-timescales-card

December 2021:

Date at which an amendment to a previously accepted planning permission for a teaching building on the Headington Hill site was submitted.

March 2022:

Date at which a planning application was submitted to Oxford City Council for the workshop building on the Headington Hill site.

June 2022:

Date at which planning permission was granted for both the  workshop and teaching buildings.

November 2022:

Date at which we expect initial enabling works for the buildings to begin. 

December 2022:

Date at which we expect construction work for the buildings to begin.

2024-25 academic year:

Date at which we currently expect the teaching and workshop buildings to open their doors.