Gipsy Lane works from 22 November

Notice valid from: 22/11/2013 - 30/11/2013

Expected programme of works from 22 November to 30 November

What's happening on site

 

  • Main lecture theatre and teaching rooms are complete
  • Lighting and flooring have been completed in The Terrace
  • See recent images from the construction site on our Twitter image gallery

 

What you need to know

Everybody

 

  • A section of the Piazza, the Abercrombie exterior staircase cut through and Abercrombie entrance automatic doors on level 1 are predicted to be open by the beginning of December.
  • Deliveries to the Print Room, International Centre and Tonge will need to be arranged in advance - please contact spacetothink@brookes.ac.uk for further information

 

Buckley and Abercrombie

 

  • New bike parking has been installed close to the building entrance.

 

Sinclair

 

  • Finishes applied to the courtyard close to Sinclair will require some occasional drilling of block work and may cause minor disruption

 

Tonge and International Centre

 

  • The stairs between these two buildings have been reopened
  • Work outside the International Centre is in its final stages and may cause minor disruption from trimming equipment and hand tools

 

Media Centre

 

  • Excavation work has been completed outside of the media centre
  • Paving work will continue in this area into the beginning of December
  • This work may cause some noise disruption to building users

 

To receive weekly updates please email spacetothink@brookes.ac.uk