Gipsy Lane works from 25 October 2013

Notice valid from: 25/10/2013 - 03/11/2013

Expected programme of works from 25 October 2013 to 1 November 2013

What's happening on site

Top two levels of cladding have been fitted to the colonnade

Paving on the piazza and the Western Access road is well underway

Lighting is active across the building

Main lecture theatre and teaching rooms are complete

See recent images from the construction site at our Twitter image gallery

What you need to know

Everybody

Minor alterations to the footpath to the Media Centre, International Centre and Tonge will continue into the beginning of November

The building access will not be affected

The bike parking outside the Media Centre will be closed at the beginning of November, an alternative bike park is being installed outside of the Buckley building

Deliveries to the Print Room, International Centre and Tonge will need to be arranged in advance - please contact spacetothink@brookes.ac.uk for further info

Gibbs and John Payne

Paving work behind Gibbs is in its final stages

Tarmac work in the road between these two buildings will take place at the end of October for no more than one week

Grinding, cutting and excavation work may cause erratic disruption to nearby building users

Buckley and Abercrombie

New bike parking will be installed close to the building entrance by the end of the month

Whilst bike racks are being fitted there will be some noise disruption to building users

Sinclair

Finishes applied to the courtyard close to Sinclair will require some occasional drilling of block work and may cause minor disruption

This work is expected to complete by the end of the month

Tonge and International Centre

The stairs between these two buildings are expected to be reopened before the end of the month

The steps at the front of Tonge are expected to be opened next week

Paving work outside the International Centre is in its final stages and may cause minor disruption from trimming equipment and hand tools

Media Centre

Excavation work on the site of the bike parking loops next to the building will take place at the beginning of November

This work may cause some noise disruption to building users

As part of the paving work, access to the building may need to be closed for up to two days

Advanced notice will be given and the work will be programmed for non-working hours if possible

To receive weekly updates please email spacetothink@brookes.ac.uk